five

Probabilistic risk analysis for elevated metro rail construction using Monte Carlo simulations

收藏
DataCite Commons2025-12-23 更新2026-04-25 收录
下载链接:
https://tandf.figshare.com/articles/dataset/Probabilistic_risk_analysis_for_elevated_metro_rail_construction_using_Monte_Carlo_simulations/30940951
下载链接
链接失效反馈
官方服务:
资源简介:
Metro rail projects in rapidly urbanizing regions often face schedule delays and cost overruns due to uncertainty and complex risk interactions. This study presents a Monte Carlo simulation–based framework for probabilistic risk analysis in elevated metro rail construction by integrating deterministic scheduling in Primavera P6 with risk modelling in Risk Analyzer. The framework comprises baseline scheduling, uncertainty integration, risk modelling, mitigation planning, and sensitivity analysis. A baseline schedule of 711 days with an estimated cost of ₹2,598.8 million was developed, and 1,000 Monte Carlo simulations were conducted using three-point estimates for activity duration and cost. Seventeen project risks were identified and prioritised using a probability–impact approach. Activity uncertainties increased the mean project duration to 778 days (9.4%), with a maximum of 831 days, while the mean cost marginally increased to ₹2,601.7 million. Considering all risks, the mean duration increased to 842 days (18.4%), with a maximum of 1,008 days, and the mean cost rose to ₹2,621.7 million. A mitigation plan costing ₹3.32 million reduced mean and maximum durations by 26 and 76 days, respectively, yielding potential savings of up to ₹23.1 million. Sensitivity analysis identified critical activities requiring proactive management, demonstrating the framework’s effectiveness in improving schedule reliability and cost control.
提供机构:
Taylor & Francis
创建时间:
2025-12-23
5,000+
优质数据集
54 个
任务类型
进入经典数据集
二维码
社区交流群

面向社区/商业的数据集话题

二维码
科研交流群

面向高校/科研机构的开源数据集话题

数据驱动未来

携手共赢发展

商业合作