资源简介:

Table 8.1: Potentially significant environmental impact during construction and operation phase and their mitigation measures Proposed project activitiesPotentially Significant ImpactsMitigation measuresImplementation responsibilitySupervising responsibility450 MW CCPPImpact on socialPre-constructionlife andand designenvironment:impactsa. Survey and landa. Possibility ofa. The land is within thea. EGCB Ltd.a. Managingallocationdamage of ecologycompound of SiddhirganjDirector –EGCBand agriculturalPower Plant and there isLtd.fieldno ecological area withinthe compoundb. Displacement ofb. Dislocation ofb. EGCB Ltd., own theb. EGCB Ltd.b. Managing