The monitoring results after the implementation of UHPC lining
收藏DataCite Commons2025-06-03 更新2026-05-05 收录
下载链接:
https://www.scidb.cn/detail?dataSetId=daaf09e8e9e84b38a22fb328121d7deb
下载链接
链接失效反馈官方服务:
资源简介:
Data were obtained through on-site monitoring. The subsidence at the monitoring points aligns with G1, G2, and G3. After the primary support construction of the second layer, the average displacement of the support ranged from 1.2 mm/d to 1.4 mm/d. Before the invert construction, the average displacement of the support ranged from 1.2 mm/d to 1.7 mm/d. After the invert construction, the average displacement of the support decreased to a range of 0.4 mm/d to 0.5 mm/d.
提供机构:
Science Data Bank
创建时间:
2025-06-03