Segment Three Data of Persian Gulf Industrial Water Transfer to Yazd
收藏资源简介:
This dataset contains the monthly planned and actual progress data for Segment Three of the Persian Gulf Water Transfer to Southeast Industries project, covering the period from April 2018 (Farvardin 1397) to December 2020 (Azar 1399). Segment Three involves the transfer of industrial water from the Sarcheshmeh Mine area to the Chadormalu Steel Complex in Ardakan, Yazd. The project execution is divided into three construction sites, and the dataset records key metrics for each site, including monthly plans, actual monthly progress, cumulative planned progress, cumulative actual progress, and deviations between planned and actual cumulative progress. This data is crucial for monitoring, evaluating, and managing the progress of this significant industrial water supply initiative aimed at supporting mining and industrial activities in the region.
本数据集涵盖波斯湾向东南部工业输水项目(Persian Gulf Water Transfer to Southeast Industries project)第三标段的月度计划与实际进度数据,时间跨度为2018年4月(伊朗历1397年法尔万月,Farvardin 1397)至2020年12月(伊朗历1399年阿扎尔月,Azar 1399)。第三标段负责将工业用水从萨尔切什梅(Sarcheshmeh)矿区输送至亚兹德省阿尔达坎市的查多马卢钢铁联合企业(Chadormalu Steel Complex)。该项目施工分为三个施工现场,本数据集记录了各施工现场的关键指标,包括月度计划进度、月度实际进度、累计计划进度、累计实际进度以及累计计划与实际进度偏差。该数据集对于监测、评估与管控这项旨在支撑本地区采矿与工业活动的重要工业供水项目的进度至关重要。