Table E-0-11: Monitoring of Air Quality and Noise level during construction phase (Originally Table 7) ParametersMonitoring FrequencyResource Required and ResponsibilityCommentParticulate Matter (PM10, PM2.5)Once every 3 months, and as directed by the PDPM10 and PM2.5 measuring equipment; Contractor’s responsibilityResults to be verified by the Environmental Expert of DSC team.Noise LevelOnce every month, and as directed by the PDNoise level meter; Contractor’s responsibilitySurface Water Quality (pH, Turbidity, BOD, COD, TDS, DO, Ammonia (NH3-N)Once every Quarter and as directed by PDFrom Accredited Laboratory; Contractor’s responsibilityResults to be verified by the Environmental Expert of DSC team.