Data for: Construction Time, Cost and Testing Data of a Prefabricated Isolation Medical Unit for COVID-19
收藏Mendeley Data2026-04-18 收录
下载链接:
https://data.mendeley.com/datasets/7t22d8dmn6
下载链接
链接失效反馈官方服务:
资源简介:
The data presented have been gathered under the construction of a high cleanness negative pressure prefabricated isolation medical unit constructed for COVID-19 patients located at Pingshan People’s Hospital, Shenzhen, China. Under this project, this medical unit was constructed within five working days via prefabricated modular construction. The collected installation cost data were categorized as various major components, including the container, windows & doors, sanitation, indoor equipment, heating, ventilation and air conditioning. All the costs listed are in CNY (Chinese Yuan).
本次采集的数据集源自中国深圳市坪山人民医院为新型冠状病毒肺炎(COVID-19)患者搭建的高洁净负压预制模块化隔离医疗单元的建设项目。本项目采用预制模块化施工工艺,仅用5个工作日即完成该医疗单元的搭建。所采集的安装成本数据已按主要组成部分分类,涵盖集装箱、门窗、卫生设施、室内设备、供暖、通风与空调系统。所有所列成本均以人民币(CNY)计价。
创建时间:
2021-04-26



